Sea-Tac Airport to open Third Runway

19 November 2008, 11:11 am

Sea-Tac Airport will open its third runway on Thursday, November 20th, 2008 after 16 years of development and costs more than $1 billion.

Sea-Tac's new third runway is designed to help decrease delays during low visibility conditions, which occur approximately 44% of the year. The third runway will allow two streams of traffic to land in lower visibility conditions. Currently, Sea-Tac's two runways are too close to each other to allow two streams of traffic to arrive in such condition.

Runway Facts:

  • 8,500 feet long
  • 150 feet wide
  • 17 inches thick
  • Designed to last 40 years
  • 130,000 cubic yards of concrete were used
  • 35,000 tons of asphalt

Previous Posts: